Sunday, November 6, 2011

Lock Up stage!

Ensuite and WIR in main bedroom

Another view of Ensuite in main bedroom

Main bedroom

Entry

Dining and living Area


bathroom2

Rumpus room

Rumpus room with Backyard


Kitchen view from Living area



Bed 3



bed 4


Bed 2


Living and Alfresco

Living , dining and alfresco

Study room

Theater room



bed 1 from Ensuite with WIR on left

Double garage

gable facade

Drysdale30

Drysdale 30 street view


Wednesday, November 2, 2011

Updates

Will be going this weekend again to check the bricklaying, and Internals doors,
Will decide onwards if we need practical Inspection for each stage or at the end.
The front door has been delievered , however It has be painted to the actual colour we have ordered

Design and the house dimensions


Frame done, Internal ducted fitting

Ducted Heating and Kitchen

Bathroon 2





Alfresco with Concrete Pole

Brick Laying

Roof tiling were finished ,
Brick laying started on the site
Double garage

Gable Facade


Backyard


Side Access


Initial process


After months of delay , The land was finally settled.
Porter davies for the contrsuction.
We have gone with Drysdale 30 , with few extra upgrades.
The land was titles in August for Stage 22 in bluestone green.

Site started on 15th of sep2011
SLAB was done and Frame was erected with 3 weeks .
Roof Tiling started on 1st of October 2011.